FOR IMMEDIATE RELEASE
June 25, 2021
Over $25 Million
Investment in the City of Kingston Midtown Corridor; Multiple Projects Underway
KINGSTON, NY – Mayor Steven T. Noble is
pleased to provide an update on the various construction projects currently
underway in the City of Kingston. The projects along the Broadway corridor,
including the I-587 Roundabout, Broadway Streetscape, the emergency sewer repairs,
and the Broadway/Grand Intersection Realignment, combined make up an over $25
million investment in the center of our community. Of the four major projects,
the majority of construction work will be wrapping up by the end of the summer.
The I-587 Roundabout
project is funded and operated by the New York State DOT and is designed to
reduce delays and improve safety for all travelers. While minimizing impact to
area residents and businesses, the Roundabout will preserve parking capacity,
enhance economic vitality, protect the historical character of the area, and
will provide a beautiful gateway into the City of Kingston.
Construction began in 2020, and after
several temporary configurations, is now in the final construction phase. Night
work to pave the Roundabout project area is tentatively scheduled for July
12-13, 2021. Construction is expected to be completed by the end of July.
Landscaping and tree planting will occur in the September planting
season. Total investment $11,890,426
The Broadway
Streetscape project renovates and rejuvenates Broadway from the I-587
Roundabout project to Grand Street and will include new ADA accessible
sidewalks, a dedicated bicycle lane, many amenities including new light poles,
76 healthy street trees, 22 benches, 23 trash/recycling cans, 28 bike racks and
paving of the entire project area. This portion of Broadway also makes
connections on the Kingston Greenline and Empire State Trail.
Construction began in 2020 with new
sidewalks on the west side of Broadway and currently continues on the east side
of Broadway. All sidewalk construction is expected to be completed in early
August. Additional amenities will be added in August, and the project will
culminate in paving. The entire project is expected to be completed by September
15, 2021. Total investment $9,133,248
The emergency Broadway sewer project
installs new sanitary sewer pipes to replace old, failing sewer lines along
Broadway from Cedar Street to East St. James Street.
Construction began in February 2021
required significant lane changes and no parking in the project area so that
the deteriorating sewer system below Broadway could be accessed. Reconstruction
of the area has begun, and paving of the project area will occur in the next
couple of weeks. The project is expected to be completed by July 2,
2021. Total investment
$2,800,000
The Broadway/Grand Intersection
Realignment project will redesign the intersection of Broadway, Grand
Street, Pine Grove Avenue, and Prince Street to improve traffic safety for
motorists, bicyclists and pedestrians and included the demolition of the former
Planet Wings building. The intersection is currently confusing and difficult to
navigate. The realignment will allow an opportunity for the community to
conceptualize uses for the newly-created public green space.
Construction is expected to begin on July
9, 2021 and will dovetail with the Broadway Streetscape work. The intersection
will be configured into the new design by mid-October, and the project is
expected to be completed by October 31, 2021. Due to material shortage,
light poles in the project area are expected to be installed by the end of the
year. Total investment $1,525,000
“These projects make up the single biggest
investment to infrastructure in the City of Kingston’s long history,” said
Mayor Noble. “We are not only improving vital infrastructure, but we are
creating an attractive and inviting gateway to our City, and providing the
Midtown Business District with a beautiful thoroughfare. These projects provide
a healthier, safer environment and create more equitable pathways through our
City. We know the construction can be frustrating, but this is an important
step in the continued revitalization of the neighborhood.”
In addition to all of the roadwork along
the Broadway corridor, reconstruction of the Elmendorf Bridge is expected to
begin in July and completed this fall. The project is not expected to cause
traffic delays on Broadway. Total projected cost: $1,040,000
Also in Midtown, Ulster County is
currently in construction on the Midtown Linear Park trail, which runs from
Kingston Plaza to Cornell Street, adding another $2.5 million investment in the
area. The Midtown Linear Park trail will be paved and will also serve as a
connector on the Kingston Greenline. Part of the larger Empire State Trail, the
Kingston Greenline connects on the west to the O&W Trail and the Wallkill
Valley Trail, weaves through the City complete streets, improved sidewalks,
bike lanes, and linear parks, then connects to the Hudson River Brickyard
Trail.
The City of Kingston provides weekly
roadwork updates at: https://www.kingston-ny.gov/news/?FeedID=1354